Large power and GSU transformers, Q4 2023: Wood Mackenzie

Large power transformer and GSU lead times averaged 120 to 130 weeks in Q4 2023.

120–130 weeks Large power · Q4 2023 · US

“As large developers and utilities increase transformer orders, lead times for large power transformers and generator step-up units have surged to 120–130 weeks on average as of the fourth quarter of 2023, with no signs of relief.”
Class on the chart
Large power and substation transformers
Transformer type
Large power transformer and GSU
Size / class
Large power / GSU
Region
US
As of
2023-Q4
Lead time, low (weeks)
120
Lead time, high (weeks)
130
Lead time as stated
Average of 120 to 130 weeks
Publisher
Wood Mackenzie (via POWER)
Source type
secondary
Verified

Sources

  1. The Transformer Crisis: An Industry on the Brink (POWER, 26 Jun 2024) accessed 2026-11-09

Cite this reading

Wood Mackenzie (via POWER), as compiled by Transformer Lead Times: “Large power and GSU transformers, Q4 2023: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-q4-2023-lpt-gsu/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie