Power transformers, Q2 2025: Wood Mackenzie

Wood Mackenzie's lead time benchmark put average power transformer lead times at 128 weeks in 2025 Q2.

128 weeks Large power · Q2 2025 · US

“Power transformer lead times eased in Q2 falling by 10 weeks to an average of 128 weeks.”
Class on the chart
Large power and substation transformers
Transformer type
Power transformer
Size / class
Power transformer (classified by type, not voltage)
Region
US
As of
2025-Q2
Lead time, low (weeks)
128
Lead time, high (weeks)
128
Lead time as stated
Average 128 weeks after receipt of order (chart value). Source: Wood Mackenzie Supply Chain’s Lead Time Benchmarking (chart 'Quarterly lead time change 2025 Q1 – 2025 Q2', weeks ARO).
Publisher
Wood Mackenzie
Source type
primary
Verified

Sources

  1. Wood Mackenzie: Making the connection: meeting the electric T&D supply chain challenge, Executive Summary, September 2025 (with American Clean Power) accessed 2026-11-09

Cite this reading

Wood Mackenzie, as compiled by Transformer Lead Times: “Power transformers, Q2 2025: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-power-2025q2/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q1 2025 138.4 weeks Power transformer Wood Mackenzie
Feb 2025 Three to six years Transmission-scale power transformer Hitachi Energy (via Utility Dive)