Large substation transformers, July 2026: utility via Reuters

Roseville Electric’s CEO told Reuters large substation transformers were taking more than three years, so the California utility buys equipment five years ahead.

Pushing past three years Large power · Jul 2026 · US

“But with large transformers for substations pushing past a three-year waiting time, the utility is buying equipment for projects that it knows are coming five years in advance, he added.”
Class on the chart
Large power and substation transformers
Transformer type
Large substation transformer
Size / class
Large substation
Region
US
As of
2026-07
Lead time as stated
Pushing past three years
Publisher
Reuters (Roseville Electric CEO Dan Beans)
Source type
utility
Verified

Sources

  1. Reuters via Kitco: US power companies scramble to secure equipment as surging data center demand strains supplies (9 Jul 2026) accessed 2026-11-09

Cite this reading

Reuters (Roseville Electric CEO Dan Beans), as compiled by Transformer Lead Times: “Large substation transformers, July 2026: utility via Reuters”. https://transformerleadtimes.com/utility-substation-2026/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie
Feb 2025 Three to six years Transmission-scale power transformer Hitachi Energy (via Utility Dive)