Large transformers (100 MVA+), Feb 2026: BloombergNEF via pv magazine

BloombergNEF data show lead times for large transformers of 100 MVA and above have more than doubled since 2019, with US transformer prices up 79%.

+79% Large power · Feb 2026 · US

“Data from market intelligence provider BloombergNEF show that lead times for supply of large transformers (100 megavolt-amp and above) have more than doubled compared to 2019, and in the US market prices for transformers have increased by 79%.”
Class on the chart
Large power and substation transformers
Transformer type
Large power transformer
Size / class
100 MVA and above
Region
US
As of
2026-02
Lead time as stated
More than doubled compared with 2019
Price change
79%
Price baseline
Not stated by the source (US market)
Publisher
BloombergNEF (via pv magazine)
Source type
secondary
Verified

Sources

  1. Global energy transition hits a hardware bottleneck (pv magazine, 27 Feb 2026) accessed 2026-11-09

Cite this reading

BloombergNEF (via pv magazine), as compiled by Transformer Lead Times: “Large transformers (100 MVA+), Feb 2026: BloombergNEF via pv magazine”. https://transformerleadtimes.com/bnef-large-2026/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie
Feb 2025 Three to six years Transmission-scale power transformer Hitachi Energy (via Utility Dive)