Power and substation transformers, Aug 2026: VAWN index

An aggregated lead time index put US power and substation transformers at 160+ weeks, citing Wood Mackenzie's 2026 read.

160+ weeks Large power · Aug 2026 · US

“The substation transformer figure is Wood Mackenzie’s 2026 read of above 160 weeks.”

Named sources report this figure differently. This is a weaker source (an aggregator read or a vendor claim); the chart shows it as a hollow, dashed mark. See the conflicts

Class on the chart
Large power and substation transformers
Transformer type
Power / substation transformer
Size / class
Power / substation
Region
US
As of
2026-08
Lead time, low (weeks)
160
Lead time as stated
160+ weeks; index says this is Wood Mackenzie's 2026 read (aggregator, not primary)
Publisher
VAWN (aggregating Wood Mackenzie)
Source type
secondary
Verified

Sources

  1. Electrical Equipment Lead Time Index (VAWN, updated 13 Aug 2026) accessed 2026-11-09

Cite this reading

VAWN (aggregating Wood Mackenzie), as compiled by Transformer Lead Times: “Power and substation transformers, Aug 2026: VAWN index”. https://transformerleadtimes.com/vawn-substation-2026/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie
Feb 2025 Three to six years Transmission-scale power transformer Hitachi Energy (via Utility Dive)