Transmission-scale transformers, early 2025: Hitachi Energy

Hitachi Energy said transmission-scale transformer lead times were three to six years, with specialized units longest.

Three to six years Large power · Feb 2025 · US

““Transmission scale unit lead times are now three years to six years, with specialized transformers taking the longest time,” he added.”
Class on the chart
Large power and substation transformers
Transformer type
Transmission-scale power transformer
Size / class
Transmission scale
Region
US
As of
2025-02
Lead time as stated
Three to six years
Publisher
Hitachi Energy (via Utility Dive)
Source type
manufacturer
Verified

Sources

  1. Transformer supply bottleneck threatens power system stability as load grows (Utility Dive, 12 Feb 2025) accessed 2026-11-09

Cite this reading

Hitachi Energy (via Utility Dive), as compiled by Transformer Lead Times: “Transmission-scale transformers, early 2025: Hitachi Energy”. https://transformerleadtimes.com/hitachi-transmission-2025/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie