Large power and GSU transformers, pre-pandemic baseline: Wood Mackenzie

Wood Mackenzie puts pre-pandemic transformer lead times at 30 to 60 weeks, depending on size and specification.

30–60 weeks Large power · 2019 · US

““For reference, pre-pandemic lead times ranged from 30–60 weeks, depending on specifications/size and if the transformer had been regularly ordered over time with a proven design (therefore allowing the manufacturing process to be streamlined),” the firm noted.”
Class on the chart
Large power and substation transformers
Transformer type
Power transformer (substation and GSU)
Size / class
Large power / GSU
Region
US
As of
2019
Lead time, low (weeks)
30
Lead time, high (weeks)
60
Lead time as stated
Pre-pandemic range, depending on specifications and size
Publisher
Wood Mackenzie (via POWER)
Original source
Wood Mackenzie, April 2024
Source type
secondary
Verified

Sources

  1. The Transformer Crisis: An Industry on the Brink (POWER, 26 Jun 2024) accessed 2026-11-09

Cite this reading

Wood Mackenzie (via POWER), as compiled by Transformer Lead Times: “Large power and GSU transformers, pre-pandemic baseline: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-prepandemic-baseline/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie