Larger transformers, April 2024: Wood Mackenzie (Utility Dive)

Utility Dive reported Wood Mackenzie's April report put larger transformer lead times at 80 to 120 weeks.

80–120 weeks Large power · Apr 2024 · US

“Larger transformer lead times range from 80 to 120 weeks, according to a Wood Mackenzie, or WoodMac, April report.”

Named sources report this figure differently. See the conflicts

Class on the chart
Large power and substation transformers
Transformer type
Larger power transformers
Size / class
Large
Region
US
As of
2024-04
Lead time, low (weeks)
80
Lead time, high (weeks)
120
Lead time as stated
80 to 120 weeks, as reported by Utility Dive; conflicts with POWER's 120 to 210
Publisher
Wood Mackenzie (via Utility Dive)
Source type
secondary
Verified

Sources

  1. Transformer supply bottleneck threatens power system stability as load grows (Utility Dive, 12 Feb 2025) accessed 2026-11-09

Cite this reading

Wood Mackenzie (via Utility Dive), as compiled by Transformer Lead Times: “Larger transformers, April 2024: Wood Mackenzie (Utility Dive)”. https://transformerleadtimes.com/woodmac-apr-2024-large-ud/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie