Large substation and GSU transformers, April 2024: Wood Mackenzie (POWER)

POWER reported Wood Mackenzie's April 2024 range for large substation and GSU transformers as 120 to 210 weeks.

120–210 weeks Large power · Apr 2024 · US

“Lead times for large transformers, both substation power transformers and generator step-up (GSU) transformers, have surged to 120 to 210 weeks—or 2.3 to 4 years.”

Named sources report this figure differently. See the conflicts

Class on the chart
Large power and substation transformers
Transformer type
Substation power and GSU
Size / class
Large
Region
US
As of
2024-04
Lead time, low (weeks)
120
Lead time, high (weeks)
210
Lead time as stated
120 to 210 weeks (2.3 to 4 years). Utility Dive reports the same April report as 80 to 120 weeks for larger transformers; NIAC/others cite 80 to 210.
Publisher
Wood Mackenzie (via POWER)
Source type
secondary
Verified

Sources

  1. The Transformer Crisis: An Industry on the Brink (POWER, 26 Jun 2024) accessed 2026-11-09

Cite this reading

Wood Mackenzie (via POWER), as compiled by Transformer Lead Times: “Large substation and GSU transformers, April 2024: Wood Mackenzie (POWER)”. https://transformerleadtimes.com/woodmac-apr-2024-large-power/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie