Large power transformers, 2023: GAO via NLR

GAO found typical large power transformers taking 30 to 36 months from purchase order to receipt, up from 12 to 18 months, as cited in DOE’s May 2026 NLR report.

30 to 36 months from purchase order to receipt (up from 12 to 18 months) Large power · 2023 · US

“However, procurement timelines for new transformers measured from purchase order to receipt have lengthened from 12–18 months to 30–36 months (U.S. Government Accountability Office 2023) for typical LPTs.”
Class on the chart
Large power and substation transformers
Transformer type
Large power transformer
Size / class
Typical LPT
Region
US
As of
2023
Lead time as stated
30 to 36 months from purchase order to receipt (up from 12 to 18 months)
Publisher
US GAO (2023), cited by the National Laboratory of the Rockies (May 2026)
Original source
U.S. Government Accountability Office 2023
Source type
government
Verified

Sources

  1. Large Power Transformer Supply Chain Gap Analysis and Domestic Content Strategies for Hydropower Rehabilitation: Supplemental Report (NLR/TP-5700-96742, May 2026) accessed 2026-11-09

Cite this reading

US GAO (2023), cited by the National Laboratory of the Rockies (May 2026), as compiled by Transformer Lead Times: “Large power transformers, 2023: GAO via NLR”. https://transformerleadtimes.com/gao-lpt-2023/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie