Transformers in Europe, May 2024: Ghent University
A Ghent University researcher said transformer lead times in Europe had doubled, with price hikes.
Lead times have doubled (no week figure) Large power · May 2024 · EU
“Joannes Laveyne, a research assistant at Ghent University's electrical energy lab, highlights the widespread impact of the shortage, noting that lead times for transformers have doubled, causing delays and price hikes across various industries.”
The record
Field definitions- Class on the chart
- Large power and substation transformers
- Transformer type
- Transformers (general)
- Size / class
- Unspecified
- Region
- EU
- As of
- 2024-05
- Lead time as stated
- Lead times have doubled (no week figure)
- Publisher
- Transformer Technology (quoting Ghent University)
- Source type
- secondary
- Verified
Sources
- Europe faces transformer shortage (Transformer Technology, 7 May 2024) accessed 2026-11-09
Cite this reading
Transformer Technology (quoting Ghent University), as compiled by Transformer Lead Times: “Transformers in Europe, May 2024: Ghent University”. https://transformerleadtimes.com/eu-ghent-2024/ (accessed 9 Nov 2026).
CC BY 4.0. Quote the original publisher; link this page for the dated record.
Other large power readings
Filter the table| As of | Reading | Publisher |
|---|---|---|
| Aug 2026 | 160+ weeks Power / substation transformer | VAWN (aggregating Wood Mackenzie) |
| Jul 2026 | Pushing past three years Large substation transformer | Reuters (Roseville Electric CEO Dan Beans) |
| May 2026 | +80% High-capacity power transformer | PwC analysts (via pv magazine, citing Reuters Events) |
| May 2026 | +80% Large power transformer | National Laboratory of the Rockies (formerly NREL), US DOE |
| May 2026 | 200+ weeks Large power transformer | Transformer Technology (citing Northfield Transformers) |
| Feb 2026 | +79% Large power transformer | BloombergNEF (via pv magazine) |
| Q2 2025 | 128 weeks Power transformer | Wood Mackenzie |
| Q1 2025 | 138.4 weeks Power transformer | Wood Mackenzie |