Large power transformers, 2010 baseline: DOE 2014 study
In 2010, large power transformers took 5 to 12 months from order to delivery from US plants and 6 to 16 months from foreign plants.
5 to 12 months (domestic), 6 to 16 months (foreign); 18 to 24 months in high-demand periods Large power · 2010 · US
“The pre-shortage baseline comes from DOE's 2014 study, drawing on USITC trade-case data: in 2010, the average lead time between an LPT order and delivery ran 5 to 12 months for domestic producers and 6 to 16 months for foreign ones, stretching toward 18 to 24 months in high-demand periods.”
The record
Field definitions- Class on the chart
- Large power and substation transformers
- Transformer type
- Large power transformer
- Size / class
- >100 MVA (LPT)
- Region
- US
- As of
- 2010
- Lead time as stated
- 5 to 12 months (domestic), 6 to 16 months (foreign); 18 to 24 months in high-demand periods
- Publisher
- US DOE (2014 study, via ReliaMag)
- Original source
- DOE 2014 LPT study using USITC trade-case data
- Source type
- secondary
- Verified
Sources
Cite this reading
US DOE (2014 study, via ReliaMag), as compiled by Transformer Lead Times: “Large power transformers, 2010 baseline: DOE 2014 study”. https://transformerleadtimes.com/doe-lpt-2010-baseline/ (accessed 9 Nov 2026).
CC BY 4.0. Quote the original publisher; link this page for the dated record.
Other large power readings
Filter the table| As of | Reading | Publisher |
|---|---|---|
| Aug 2026 | 160+ weeks Power / substation transformer | VAWN (aggregating Wood Mackenzie) |
| Jul 2026 | Pushing past three years Large substation transformer | Reuters (Roseville Electric CEO Dan Beans) |
| May 2026 | +80% High-capacity power transformer | PwC analysts (via pv magazine, citing Reuters Events) |
| May 2026 | +80% Large power transformer | National Laboratory of the Rockies (formerly NREL), US DOE |
| May 2026 | 200+ weeks Large power transformer | Transformer Technology (citing Northfield Transformers) |
| Feb 2026 | +79% Large power transformer | BloombergNEF (via pv magazine) |
| Q2 2025 | 128 weeks Power transformer | Wood Mackenzie |
| Q1 2025 | 138.4 weeks Power transformer | Wood Mackenzie |