Large power transformers, 2010 baseline: DOE 2014 study

In 2010, large power transformers took 5 to 12 months from order to delivery from US plants and 6 to 16 months from foreign plants.

5 to 12 months (domestic), 6 to 16 months (foreign); 18 to 24 months in high-demand periods Large power · 2010 · US

“The pre-shortage baseline comes from DOE's 2014 study, drawing on USITC trade-case data: in 2010, the average lead time between an LPT order and delivery ran 5 to 12 months for domestic producers and 6 to 16 months for foreign ones, stretching toward 18 to 24 months in high-demand periods.”
Class on the chart
Large power and substation transformers
Transformer type
Large power transformer
Size / class
>100 MVA (LPT)
Region
US
As of
2010
Lead time as stated
5 to 12 months (domestic), 6 to 16 months (foreign); 18 to 24 months in high-demand periods
Publisher
US DOE (2014 study, via ReliaMag)
Original source
DOE 2014 LPT study using USITC trade-case data
Source type
secondary
Verified

Sources

  1. The Aging Transformer Fleet: What the 40-Year Claim Really Says (ReliaMag, 7 Jul 2026) accessed 2026-11-09

Cite this reading

US DOE (2014 study, via ReliaMag), as compiled by Transformer Lead Times: “Large power transformers, 2010 baseline: DOE 2014 study”. https://transformerleadtimes.com/doe-lpt-2010-baseline/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other large power readings

Filter the table
As ofReadingPublisher
Aug 2026 160+ weeks Power / substation transformer VAWN (aggregating Wood Mackenzie)
Jul 2026 Pushing past three years Large substation transformer Reuters (Roseville Electric CEO Dan Beans)
May 2026 +80% High-capacity power transformer PwC analysts (via pv magazine, citing Reuters Events)
May 2026 +80% Large power transformer National Laboratory of the Rockies (formerly NREL), US DOE
May 2026 200+ weeks Large power transformer Transformer Technology (citing Northfield Transformers)
Feb 2026 +79% Large power transformer BloombergNEF (via pv magazine)
Q2 2025 128 weeks Power transformer Wood Mackenzie
Q1 2025 138.4 weeks Power transformer Wood Mackenzie