Transformer prices, April 2024: Wood Mackenzie

Wood Mackenzie said transformer prices had risen 60% to 80% on average since January 2020.

+60–80% Prices · Apr 2024 · US

“At the same time, depending on the size and application, transformer prices have risen 60% to 80% on average since January 2020, driven upward by raw material commodities.”
Class on the chart
Price indexes and price changes
Transformer type
Transformers (all)
Size / class
All sizes
Region
US
As of
2024-04
Price change
60%
Price change, high
80%
Price baseline
vs January 2020
Publisher
Wood Mackenzie (via POWER)
Source type
secondary
Verified

Sources

  1. The Transformer Crisis: An Industry on the Brink (POWER, 26 Jun 2024) accessed 2026-11-09

Cite this reading

Wood Mackenzie (via POWER), as compiled by Transformer Lead Times: “Transformer prices, April 2024: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-apr-2024-price/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other prices readings

Filter the table
As ofReadingPublisher
Sep 2026 +85.9% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Jan 2026 +78.4% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Mar 2025 +21% Pole-mounted distribution transformer Wood Mackenzie
Mar 2025 +15% Power transformer Wood Mackenzie
Mar 2025 +18% Pad-mount single-phase distribution transformer Wood Mackenzie
Mar 2025 +8% Substation transformer Wood Mackenzie
Mar 2025 +20% Pad-mount three-phase distribution transformer Wood Mackenzie
Jan 2025 +69.6% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)