US producer prices for transformers, 2026-09: BLS PPI

The BLS producer price index for electric power and specialty transformer manufacturing stood at 475.065 in 2026-09, 85.9% above January 2020.

+85.9% Prices · Sep 2026 · US

“PCU335311335311 index: 2020-01 = 255.5; 2026-09 = 475.065”
Class on the chart
Price indexes and price changes
Transformer type
Electric power and specialty transformers (industry PPI)
Size / class
All
Region
US
As of
2026-09
Price change
85.9%
Price baseline
vs January 2020 (index 255.5); calculated from FRED index values, not seasonally adjusted
Publisher
US Bureau of Labor Statistics (via FRED)
Source type
primary
Verified

Sources

  1. FRED / BLS: PPI by Industry: Electric Power and Specialty Transformer Manufacturing (PCU335311335311) accessed 2026-11-09

Cite this reading

US Bureau of Labor Statistics (via FRED), as compiled by Transformer Lead Times: “US producer prices for transformers, 2026-09: BLS PPI”. https://transformerleadtimes.com/ppi-transformer-mfg-2026-09/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other prices readings

Filter the table
As ofReadingPublisher
Jan 2026 +78.4% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Mar 2025 +21% Pole-mounted distribution transformer Wood Mackenzie
Mar 2025 +15% Power transformer Wood Mackenzie
Mar 2025 +18% Pad-mount single-phase distribution transformer Wood Mackenzie
Mar 2025 +8% Substation transformer Wood Mackenzie
Mar 2025 +20% Pad-mount three-phase distribution transformer Wood Mackenzie
Jan 2025 +69.6% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
2025 up to +95% Distribution transformer Wood Mackenzie (via POWER)