US producer prices for transformers, 2026-01: BLS PPI
The BLS producer price index for electric power and specialty transformer manufacturing stood at 455.931 in 2026-01, 78.4% above January 2020.
+78.4% Prices · Jan 2026 · US
“PCU335311335311 index: 2020-01 = 255.5; 2026-01 = 455.931”
The record
Field definitions- Class on the chart
- Price indexes and price changes
- Transformer type
- Electric power and specialty transformers (industry PPI)
- Size / class
- All
- Region
- US
- As of
- 2026-01
- Price change
- 78.4%
- Price baseline
- vs January 2020 (index 255.5); calculated from FRED index values, not seasonally adjusted
- Publisher
- US Bureau of Labor Statistics (via FRED)
- Source type
- primary
- Verified
Sources
Cite this reading
US Bureau of Labor Statistics (via FRED), as compiled by Transformer Lead Times: “US producer prices for transformers, 2026-01: BLS PPI”. https://transformerleadtimes.com/ppi-transformer-mfg-2026-01/ (accessed 9 Nov 2026).
CC BY 4.0. Quote the original publisher; link this page for the dated record.
Other prices readings
Filter the table| As of | Reading | Publisher |
|---|---|---|
| Sep 2026 | +85.9% Electric power and specialty transformers (industry PPI) | US Bureau of Labor Statistics (via FRED) |
| Mar 2025 | +21% Pole-mounted distribution transformer | Wood Mackenzie |
| Mar 2025 | +15% Power transformer | Wood Mackenzie |
| Mar 2025 | +18% Pad-mount single-phase distribution transformer | Wood Mackenzie |
| Mar 2025 | +8% Substation transformer | Wood Mackenzie |
| Mar 2025 | +20% Pad-mount three-phase distribution transformer | Wood Mackenzie |
| Jan 2025 | +69.6% Electric power and specialty transformers (industry PPI) | US Bureau of Labor Statistics (via FRED) |
| 2025 | up to +95% Distribution transformer | Wood Mackenzie (via POWER) |