US producer prices for power and distribution transformers, 2022-01: BLS PPI

The BLS producer price index for power and distribution transformers (except parts) stood at 275.554 in 2022-01, 36.8% above January 2020.

+36.8% Prices · Jan 2022 · US

“PCU3353113353111 index: 2020-01 = 201.5; 2022-01 = 275.554”
Class on the chart
Price indexes and price changes
Transformer type
Power and distribution transformers, except parts (product PPI)
Size / class
All
Region
US
As of
2022-01
Lead time as stated
Series last published 2023-02
Price change
36.8%
Price baseline
vs January 2020 (index 201.5); calculated from FRED index values
Publisher
US Bureau of Labor Statistics (via FRED)
Source type
primary
Verified

Sources

  1. FRED / BLS: PPI: Power and Distribution Transformers, Except Parts (PCU3353113353111) accessed 2026-11-09

Cite this reading

US Bureau of Labor Statistics (via FRED), as compiled by Transformer Lead Times: “US producer prices for power and distribution transformers, 2022-01: BLS PPI”. https://transformerleadtimes.com/ppi-power-distribution-2022-01/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other prices readings

Filter the table
As ofReadingPublisher
Sep 2026 +85.9% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Jan 2026 +78.4% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Mar 2025 +21% Pole-mounted distribution transformer Wood Mackenzie
Mar 2025 +15% Power transformer Wood Mackenzie
Mar 2025 +18% Pad-mount single-phase distribution transformer Wood Mackenzie
Mar 2025 +8% Substation transformer Wood Mackenzie
Mar 2025 +20% Pad-mount three-phase distribution transformer Wood Mackenzie
Jan 2025 +69.6% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)