Distribution and large power transformer prices, 2020 to 2024: CRS

CRS, using BLS data, said distribution and large power transformer prices rose roughly 40% from 2020 to 2024 after inflation.

+40% Prices · 2024 · US

“The price of transformers has increased sharply since 2020, with data from the Bureau of Labor Statistics reporting the prices of both distribution transformers and large power transformers to have risen roughly 40% from 2020 to 2024 (inflation-adjusted).”
Class on the chart
Price indexes and price changes
Transformer type
Distribution and large power transformers
Size / class
All
Region
US
As of
2024
Price change
40%
Price baseline
vs 2020, inflation-adjusted
Publisher
Congressional Research Service (BLS data)
Source type
government
Verified

Sources

  1. CRS R48933: Electricity Distribution Transformers: Supply, Tariffs, and Policy Options (23 Apr 2026) accessed 2026-11-09

Cite this reading

Congressional Research Service (BLS data), as compiled by Transformer Lead Times: “Distribution and large power transformer prices, 2020 to 2024: CRS”. https://transformerleadtimes.com/crs-bls-price-2020-2024/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other prices readings

Filter the table
As ofReadingPublisher
Sep 2026 +85.9% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Jan 2026 +78.4% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)
Mar 2025 +21% Pole-mounted distribution transformer Wood Mackenzie
Mar 2025 +15% Power transformer Wood Mackenzie
Mar 2025 +18% Pad-mount single-phase distribution transformer Wood Mackenzie
Mar 2025 +8% Substation transformer Wood Mackenzie
Mar 2025 +20% Pad-mount three-phase distribution transformer Wood Mackenzie
Jan 2025 +69.6% Electric power and specialty transformers (industry PPI) US Bureau of Labor Statistics (via FRED)