Distribution transformers, 2018: ERMCO

ERMCO's CEO said distribution transformers arrived 12 to 14 weeks after an order in 2018.

12–14 weeks Distribution, all · 2018 · US

“They’d pick up the phone or they’d shoot over a PO, and in anywhere from 12 to 14 weeks, that transformer was showing up in their doorstep.”
Class on the chart
Distribution transformers, all types including pole-mount
Transformer type
Distribution transformer
Size / class
Distribution (single- and three-phase)
Region
US
As of
2018
Lead time, low (weeks)
12
Lead time, high (weeks)
14
Lead time as stated
12 to 14 weeks from purchase order to delivery
Publisher
Latitude Media (Catalyst podcast, ERMCO CEO Tim Mills)
Source type
manufacturer
Verified

Sources

  1. Understanding the electric transformer shortage (Latitude Media, 26 Feb 2024) accessed 2026-11-09

Cite this reading

Latitude Media (Catalyst podcast, ERMCO CEO Tim Mills), as compiled by Transformer Lead Times: “Distribution transformers, 2018: ERMCO”. https://transformerleadtimes.com/ermco-distribution-2018/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other distribution, all readings

Filter the table
As ofReadingPublisher
Feb 2024 Up to two years (4x pre-2022) Distribution transformer NREL (via pv magazine USA)
Feb 2024 As long as two years for single- and three-phase pad-mount units Pad-mounted distribution transformer Latitude Media (ERMCO CEO Tim Mills)
2024 Over two years (vs three months in 2018) Distribution transformer American Public Power Association
2023 12 months or more (vs three months in 2018) Distribution transformer American Public Power Association
2022 About 12 months average; some quotes over three years; +429% vs pre-2021 Distribution transformer American Public Power Association
2020 About two to three months pre-2021 Distribution transformer American Public Power Association