Distribution transformers, pre-2021: APPA survey
Public power utilities said distribution transformers took about two to three months to procure before 2021.
About two to three months pre-2021 Distribution, all · 2020 · US
“Meanwhile, between 2020 and 2022, average lead times to procure distribution transformers for all voltage classes rose 429% for public power respondents -- from about two to three months pre-2021 to about 12 months in 2022.”
The record
Field definitions- Class on the chart
- Distribution transformers, all types including pole-mount
- Transformer type
- Distribution transformer
- Size / class
- All voltage classes
- Region
- US
- As of
- 2020
- Lead time as stated
- About two to three months pre-2021
- Publisher
- American Public Power Association
- Source type
- industry-association
- Verified
Sources
Cite this reading
American Public Power Association, as compiled by Transformer Lead Times: “Distribution transformers, pre-2021: APPA survey”. https://transformerleadtimes.com/appa-distribution-2020/ (accessed 9 Nov 2026).
CC BY 4.0. Quote the original publisher; link this page for the dated record.
Other distribution, all readings
Filter the table| As of | Reading | Publisher |
|---|---|---|
| Feb 2024 | Up to two years (4x pre-2022) Distribution transformer | NREL (via pv magazine USA) |
| Feb 2024 | As long as two years for single- and three-phase pad-mount units Pad-mounted distribution transformer | Latitude Media (ERMCO CEO Tim Mills) |
| 2024 | Over two years (vs three months in 2018) Distribution transformer | American Public Power Association |
| 2023 | 12 months or more (vs three months in 2018) Distribution transformer | American Public Power Association |
| 2022 | About 12 months average; some quotes over three years; +429% vs pre-2021 Distribution transformer | American Public Power Association |
| 2018 | 12–14 weeks Distribution transformer | Latitude Media (Catalyst podcast, ERMCO CEO Tim Mills) |