Distribution transformers, 2022: APPA survey

Public power utilities reported distribution transformer lead times of about 12 months in 2022, up 429%, with some quotes above three years.

About 12 months average; some quotes over three years; +429% vs pre-2021 Distribution, all · 2022 · US

“Some utilities reported being quoted lead times of more than three years.”
Class on the chart
Distribution transformers, all types including pole-mount
Transformer type
Distribution transformer
Size / class
All voltage classes
Region
US
As of
2022
Lead time as stated
About 12 months average; some quotes over three years; +429% vs pre-2021
Publisher
American Public Power Association
Source type
industry-association
Verified

Sources

  1. APPA Survey of Members Shows Distribution Transformer Production Not Meeting Demand accessed 2026-11-09

Cite this reading

American Public Power Association, as compiled by Transformer Lead Times: “Distribution transformers, 2022: APPA survey”. https://transformerleadtimes.com/appa-distribution-2022/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other distribution, all readings

Filter the table
As ofReadingPublisher
Feb 2024 Up to two years (4x pre-2022) Distribution transformer NREL (via pv magazine USA)
Feb 2024 As long as two years for single- and three-phase pad-mount units Pad-mounted distribution transformer Latitude Media (ERMCO CEO Tim Mills)
2024 Over two years (vs three months in 2018) Distribution transformer American Public Power Association
2023 12 months or more (vs three months in 2018) Distribution transformer American Public Power Association
2020 About two to three months pre-2021 Distribution transformer American Public Power Association
2018 12–14 weeks Distribution transformer Latitude Media (Catalyst podcast, ERMCO CEO Tim Mills)