Three-phase pad-mount transformers, Q1 2025: Wood Mackenzie

Wood Mackenzie's lead time benchmark put average pad-mount three-phase distribution transformer lead times at 30 weeks in 2025 Q1.

30 weeks Pad-mount 3-phase · Q1 2025 · US

“Chart value 30 weeks (2025-Q1); see page 5 of the executive summary.”

Named sources report this figure differently. See the conflicts

Class on the chart
Three-phase pad-mount distribution transformers
Transformer type
Pad-mount three-phase distribution transformer
Size / class
Pad-mounted 3-phase
Region
US
As of
2025-Q1
Lead time, low (weeks)
30
Lead time, high (weeks)
30
Lead time as stated
Average 30 weeks after receipt of order (chart value). Source: Wood Mackenzie Supply Chain’s Lead Time Benchmarking (chart 'Quarterly lead time change 2025 Q1 – 2025 Q2', weeks ARO).
Publisher
Wood Mackenzie
Source type
primary
Verified

Sources

  1. Wood Mackenzie: Making the connection: meeting the electric T&D supply chain challenge, Executive Summary, September 2025 (with American Clean Power) accessed 2026-11-09

Cite this reading

Wood Mackenzie, as compiled by Transformer Lead Times: “Three-phase pad-mount transformers, Q1 2025: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-padmount3-2025q1/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other pad-mount 3-phase readings

Filter the table
As ofReadingPublisher
Aug 2026 40+ weeks Pad-mount three-phase distribution transformer Giga Energy
Q2 2025 46.4 weeks Pad-mount three-phase distribution transformer Wood Mackenzie
Feb 2025 Double or triple pre-pandemic lead times Pad-mounted distribution transformer Hitachi Energy (via Utility Dive)