Pad-mounted distribution transformers, early 2025: Hitachi Energy
Hitachi Energy said pad-mounted distribution transformer lead times were double or triple pre-pandemic levels.
Double or triple pre-pandemic lead times Pad-mount 3-phase · Feb 2025 · US
“Lead times for pad-mounted distribution transformers “are double or triple” what they were pre-pandemic”
The record
Field definitions- Class on the chart
- Three-phase pad-mount distribution transformers
- Transformer type
- Pad-mounted distribution transformer
- Size / class
- Pad-mounted
- Region
- US
- As of
- 2025-02
- Lead time as stated
- Double or triple pre-pandemic lead times
- Publisher
- Hitachi Energy (via Utility Dive)
- Source type
- manufacturer
- Verified
Sources
Cite this reading
Hitachi Energy (via Utility Dive), as compiled by Transformer Lead Times: “Pad-mounted distribution transformers, early 2025: Hitachi Energy”. https://transformerleadtimes.com/hitachi-padmount-2025/ (accessed 9 Nov 2026).
CC BY 4.0. Quote the original publisher; link this page for the dated record.
Other pad-mount 3-phase readings
Filter the table| As of | Reading | Publisher |
|---|---|---|
| Aug 2026 | 40+ weeks Pad-mount three-phase distribution transformer | Giga Energy |
| Q2 2025 | 46.4 weeks Pad-mount three-phase distribution transformer | Wood Mackenzie |
| Q1 2025 | 30 weeks Pad-mount three-phase distribution transformer | Wood Mackenzie |