Single-phase pad-mount transformers, Q2 2025: Wood Mackenzie

Wood Mackenzie's lead time benchmark put average pad-mount single-phase distribution transformer lead times at 24 weeks in 2025 Q2.

24 weeks Pad-mount 1-phase · Q2 2025 · US

“Other key categories including pad mount 1 and 3 phase transformers, reclosers and wire & cable all recorded steady increases in Q2, while switchgear edged down to an average of 44 weeks.”

Named sources report this figure differently. See the conflicts

Class on the chart
Single-phase pad-mount distribution transformers
Transformer type
Pad-mount single-phase distribution transformer
Size / class
Pad-mounted 1-phase
Region
US
As of
2025-Q2
Lead time, low (weeks)
24
Lead time, high (weeks)
24
Lead time as stated
Average 24 weeks after receipt of order (chart value). Source: Wood Mackenzie Supply Chain’s Lead Time Benchmarking (chart 'Quarterly lead time change 2025 Q1 – 2025 Q2', weeks ARO).
Publisher
Wood Mackenzie
Source type
primary
Verified

Sources

  1. Wood Mackenzie: Making the connection: meeting the electric T&D supply chain challenge, Executive Summary, September 2025 (with American Clean Power) accessed 2026-11-09

Cite this reading

Wood Mackenzie, as compiled by Transformer Lead Times: “Single-phase pad-mount transformers, Q2 2025: Wood Mackenzie”. https://transformerleadtimes.com/woodmac-padmount1-2025q2/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.