Transformers, May 2024: Thunder Said Energy

Thunder Said Energy said lead times had risen from 12 to 24 weeks to one to three years, and prices by 70%.

+70% All sizes · May 2024 · global

“Lead times have risen from 12-24 weeks to 1-3 years.”
Class on the chart
Surveys that average all transformer sizes or do not name a type
Transformer type
Transformers (general)
Size / class
Unspecified
Region
global
As of
2024-05
Lead time as stated
1 to 3 years (from 12 to 24 weeks earlier)
Price change
70%
Price baseline
Not stated (earlier level)
Publisher
Thunder Said Energy
Source type
analyst
Verified

Sources

  1. Transformer shortages: at their core? (Thunder Said Energy, 16 May 2024) accessed 2026-11-09

Cite this reading

Thunder Said Energy, as compiled by Transformer Lead Times: “Transformers, May 2024: Thunder Said Energy”. https://transformerleadtimes.com/tse-2024/ (accessed 9 Nov 2026).

CC BY 4.0. Quote the original publisher; link this page for the dated record.

Other all sizes readings

Filter the table
As ofReadingPublisher
Feb 2025 Up to three years Transformer (unspecified) NEMA (via Utility Dive)
Apr 2024 115–130 weeks Transformers (average) Wood Mackenzie (via POWER)
2024 120–210 weeks Transformers (all, procurement) NIAC (via Utility Dive)
2021 50 weeks Transformers (all, procurement) Wood Mackenzie data cited in NIAC report (via Utility Dive)
2020 4–6 weeks Transformer (unspecified) NEMA (via Utility Dive)