Siemens Energy transformers
German energy technology group building its first US large power transformer plant in Charlotte, North Carolina.
Facts
- Headquarters
- Germany
- US manufacturing
- US plant verified
- Transformer types
- large power, GSU, mobile/rapid-response
- Product classes
- Large power, GSU, Substation
- Parent company
- –
- Announced capacity
- $150M Charlotte, North Carolina LPT plant: 57 LPTs per year, 15,000 MVA (POWER 2024); production expected early 2027 (POWER, Jan 2026).
- Checked
Sources
- Siemens Energy accessed 2026-11-09
- Wikipedia: Siemens Energy accessed 2026-11-09
- The Transformer Crisis: An Industry on the Brink (POWER, 26 Jun 2024) accessed 2026-11-09
- Transformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis? (POWER, 2 Jan 2026) accessed 2026-11-09
Makers of the same classes
All manufacturers- Delta Star
- Eaton
- Elsewedy Electric
- HD Hyundai Electric
- Hitachi Energy
- Hyosung Heavy Industries (Hyosung HICO)
- JST Power Equipment
- Končar
Lead times for these classes, sourced and dated, are on the transformer lead times tracker.